Karowe Underground Project

Client: Lucara Diamond Botswana

Main Deliverables/output:

A new 132 kV, 29 km transmission line will be constructed from the Letlhakane substation to a new 132 / 11 kV substation located within the premises of the mine.

The new 132 /11 kV substation at the mine will be integrated with the mine 11 kV network

Duration (Months): 24 On-going

Country Region: Botswana

Voltage (kV): 132 kV

Services: EPCM – Engineering, Project Management and Site Supervision

Delivering results, reliability, & rock solid dependability.

We develop quality, comprehensive, and sustainable power generation solutions for a future where society can thrive.
About Kenya International Procurement Development Agency

Kenya International Procurement Development Agency (KIPDA), has awarded many cotracts to eligible companies who handled contract supply's of different products for the development and empowerment of Africans.

Kenya International Procurement Development Agency (KIPDA), has awarded many cotracts to eligible companies who handled contract supply's of different products for the development and empowerment of Africans. KIPDA was established in 1995 as a joint venture between Fluor and Eskom.

We celebrate more than 25 years of success in providing a unique value proposition around the world because of our association and access to Eskom and Fluor intellectual property.